2017 Road Construction and Maintenance

The map and chart below show construction projects planned for Wheaton this year. Click on a point on the map for more information, or see the chart below.

Please note that dates are estimated and could be affected by weather or unforeseen circumstances.

 Legend
* - water main work included on these streets  
 2017 Road Program Status:
 Not Completed
 Completed

Types of Construction Work:

  • Street Reconstruction is the most extensive type of project. Crews remove the pavement, the base below it and sometimes the curb, then construct a new roadway.
  • Street Rehabilitation removes and replaces the curb, then resurfaces the entire pavement surface.
  • Street Resurfacing involves grinding the existing pavement in order to put down a new top layer of pavement.
  • Road maintenance includes less extensive construction, such as patching, some pavement resurfacing, and correcting potholes and surface defects.
 ANNUAL ROAD IMPROVEMENT PROGRAM
 If you have questions, please call the Engineering Department at 630-260-2065
STREET
CONSTRUCTION LIMITS
CURRENT STATUS

 RECONSTRUCTION
Crescent Street
Chase St. to President St.
Work complete
 REHABILITATION
Farnham Lane
Naperville Rd. to President St.
Work complete
 RESURFACING - SUBDIVISIONS
 Arrowhead Units 5 & 6
Barger Court
Wingate Ct. to Cul-De-Sac
Work complete
Chippewa Court
Cul-De Sac to 141 Ft South of Seneca Dr.
Work complete
Embden Lane
Milton Township Limits to Seneca Dr.
Work complete
Keim Drive
Cul-De-Sac to 141 Ft South of Seneca Dr.
Work complete
Menomini Lane
Milton Township Limits to Wingate Ct.
Work complete
Stonegate Lane
Wingate Ct. to Weisbrook Rd.
Work complete
Wingate Court
Menomini Ln. to Stonegate Ln.
Work complete
 RESURFACING
Beecher Avenue
East Leg Graf Park to Birch Dr.
Work complete
Belleau Woods Court
Belleau Woods Dr. to Cul-De-Sac
Work complete
Birch Drive
Beecher Ave. to Manchester Rd.
Work complete
Campbell Avenue
Illinois St. to Cul-De-Sac
Work complete
Carlton Avenue
North Intersection at Route 38
Begin pavement milling week of September 3rd
Evergreen Street
President St. to Ott St.
Work complete
Gary Court
Oak St. to Harrison Ave.
Begin pavement milling week of September 3rd
Hazelton Avenue
Childs St. to Manchester Rd.
Work complete
Howard Circle
Howard St. to Cul-De-Sac
Begin pavement milling week of September 3rd
Howard Street *
Harrison Ave. to Howard Cir.
Begin pavement milling week of September 3rd
Lorraine Road
North and South Intersections at Route 38
Begin pavement milling week of September 3rd
Lyford Lane
Aurora Way to Gables Blvd.
Begin pavement milling week of September 3rd
Naperville Road *
Route 38 to Willow Ave.
Begin pavement milling week of September 3rd
North Path
Blanchard St. to Pick St.
Work complete
Park Avenue *
Warrenville Rd. to Dead End
Begin pavement milling week of September 3rd
Pick Street
North Path to Harrison Ave.
Work complete
Plamondon Court *
Plamondon Rd. to Cul-De-Sac
Begin pavement milling week of September 3rd
Stoddard Avenue
Geneva Rd. to Hawthorne Blvd.
Work complete
Summit Street
Geneva Rd. to Hawthorne Blvd.
Work complete
Summit Street
Illinois St. to Harwarden St.
Work complete
Westwood Road
Beecher Ave. to Manchester Rd.
Work complete
 RESURFACING - FEDERALLY FUNDED
Gary Avenue
Harrison Avenue to Jewell Road
Work complete
Orchard Road
Summerfield Court to Wiesbrook Road
Work complete
 WATER MAIN CONSTRUCTION
County Farm Road *
Manchester Rd. to County Complex Entrance
Work complete
 ROAD MAINTENANCE PROGRAM
If you have questions, please call the Public Works Department at 630-260-2116
Aurora Way
Childs St. to Lakeside Dr.
Work complete
Blanchard Street
College Ave. to Harrison Ave.
TBD
Briarcliffe Boulevard
Doncaster Ct.
Work complete
Butterfield Ridge
Subdivision - Units 1-9
TBD
Chesterfield Avenue
Glendale Ave. to Windsor Ave.
Work Complete
Childs Street
Erie St. to Clinton Ct.
TBD
Circle Avenue
Carlton St. to Carlton St.
TBD
College Lane South
Briarcliffe Blvd. to Lancaster Ln.
TBD
Cross Street
Prairie Ave. to Dead End
Work complete
Delles Road
Roosevelt Rd. to Arbor Ave.
Work complete
Elm Street
Greenwood Dr. to Aurora Way
Work complete
Franklin Street
Gary Ave. to Carlton St.
TBD
Gables Boulevard
Commerce Dr. to Childs St.
Work Complete
Gables Boulevard
Roosevelt Rd. to Foothill Dr.
Work complete
Glendale Avenue
Sawyer Ave. to Chesterfield Ave.
Work Complete
Greenwood Drive
Elm St. to Lynwood Ln.
Work complete
Hale Street
Illinois St. to Willow Ave.
TBD
Hevern Drive
West Cul-De-Sac to East Cul-De-Sac
Work Complete
Howard Street
Cul-De-Sac to Butt Joint
Work Complete
Irving Avenue
Harrison Ave. to Jefferson Ave.
Work complete
Jefferson Avenue
Carlton St. to Ellis Ave.
TBD
Liberty Drive
Blanchard St. to Lorraine Rd.
TBD
Lois Lane
Pin Oak Ct. to St. Francis Ct.
TBD
Lowden Avenue
Blanchard St. to President St.
TBD
Lynwood Lane
Delles Rd. to Greenwood Dr.
Work complete
Lyon Avenue
Union Ave. to Dead-End
TBD
Madison Avenue
Washington St. to Irving Ave.
Work complete
Madison Avenue
Carlton St. to Ellis Ave.
TBD
Martingale Road
Bridle Ln. to Driving Park Rd.
Work complete
Pin Oak Court
Lois Ln. to Stonebridge Trl.
TBD
Prairie Avenue
President St. to Summit St.
Work Complete
Ranch Road
Driving Park Rd. to Howard Ct.
Work Complete
Sawyer Avenue
Glendale Ave. to Windsor Ave.
Work Complete
St. Francis Court
Lois Ln. to Stonebridge Trl.
TBD
Stonebridge Trail
Wiesbrook Rd. to Creekside Dr.
TBD
Stuarton Drive
Carrol Gate Rd. to Cul-De-Sac
Work Complete
Union Avenue
Western Ave. to End
TBD
Western Avenue
Lincoln Ave. to Bridge St.
TBD
Western Avenue
Union to Ave. to Lincoln Ave.
TBD
Wilshire Avenue
Sawyer Ave. to Chesterfield Ave.
Work Complete
Windsor Avenue
Sawyer Ave. to Chesterfield Ave.
Work Complete
Winner's Cup Circle
Brighton Dr. to Brighton Dr.
TBD

* water main work included on these streets – extends construction time.

Future Construction Projects

To see the list of streets for which improvements are planned over the next five years visit the Five-Year Annual Road Program.